Do I need council approval?

Do You Need Council Approval for a Concrete Slab in QLD?

The complete guide for Queensland development applications.

concrete slabbuilding approvalcut and fillstormwaterretaining wall
instantDAinstantDA Editorial Team7 min read

Key takeaways

  • A slab on its own is usually not the thing being approved — the structure it supports is.
  • Pour a slab for a shed or patio that needs building approval and the slab is assessed as part of that approval.
  • Cut or fill deeper than 1m above or below natural ground surface takes the earthworks outside the exemption.
  • A slab is an impervious surface, so the water it sheds has to reach a lawful point of discharge, not the neighbour's yard.
  • Levelling a sloping site often means a retaining wall, and retaining walls have their own thresholds.

Do You Need Council Approval for a Concrete Slab in QLD?

You'll usually hear this called a development application, or DA — that's the formal name for council approval under the Planning Act 2016. For a concrete slab, a DA almost never comes into it. The useful question is different: what is the slab for, and what did you have to do to the ground to pour it?

Get a council-ready planning report in 5 minutes — no planner, no waiting.

Get your report →
In this guide, you will learn when a slab is caught by building approval, where the earthworks thresholds sit, why levelling a sloping block is the real risk, and what your stormwater obligations are once the ground stops soaking up water.

The short answer

A bare slab poured at ground level usually needs no building approval. But if the slab supports a structure that needs approval, it is assessed as part of that approval. Cut or fill deeper than 1m, a retaining wall, or stormwater redirected onto a neighbour will each change the answer.

Decision flow asking what the slab supports, how much cut and fill is involved, and where the water goes

Figure 1: Three questions decide whether a slab is caught.

The slab is rarely the thing being approved

Building approval under the Building Act 1975 attaches to building work. A slab that forms the floor or footing system of a shed, garage, carport or roofed patio is part of that building work, and it gets assessed inside that structure's approval — footing depth, reinforcement, edge thickenings and tie-down points included. You do not apply separately for the slab.

A slab that supports nothing — a hardstand for a caravan, a path, a paved area for the bins — is generally site work rather than building work, and generally sits outside building approval.

That "generally" is doing real work. Two things commonly pull an apparently simple slab back into the system: what you did to the ground, and what you did to the water.

Cut and fill: the 1m threshold

Spend 5 minutes, not 3 weeks

instantDA generates a council-ready planning report for Queensland development applications. No town planner. No waiting.

Get your report →

Schedule 1, section 4 of the Building Regulation 2021 declares filling or excavation for a building or structure to be accepted development where the cut or fill is no deeper than 1m above or below the natural ground surface, and the embankment gradients stay within stated limits by soil type.

Maximum cut or fill without approval
1m

The gradient limits are specific. For a cut embankment: sand no steeper than 2 horizontal to 1 vertical, silt 4 to 1, firm clay 1 to 1, soft clay 3 to 2. A fill embankment must be no steeper than 4 horizontal to 1 vertical, and a compacted fill embankment is limited by soil type — sand 3 to 2, silt 4 to 1, firm clay 2 to 1.

Reference grid showing the one metre cut and fill limit, the embankment gradient limits by soil type, and the retaining wall thresholds

Figure 2: The earthworks and retaining figures that govern a slab on a sloping block.

On a flat suburban block none of this bites. On a Queensland hillside it bites immediately, because levelling a pad for a shed on a genuine slope routinely means more than a metre of difference across the site.

The retaining wall problem

Cut into a slope and something has to hold the soil back. Schedule 1, section 3 treats building work for a retaining wall as accepted development where all of the following hold.

  • No surcharge loading over the zone of influence for the wall
  • The total height of the wall and the fill or cut it retains is no more than 1m
  • The wall is no closer than 1.5m to a building or another retaining wall

The first condition is the one people miss. "Surcharge loading" means additional load applied to the soil behind the wall — a driveway, a slab, a structure. If the slab you are pouring sits within the wall's zone of influence, the wall is surcharged and the exemption does not apply, regardless of how low the wall is.

That is the common sequence: level a pad, build a low wall to hold the cut, then pour the slab right up against it. It is one job in your head and two regulated things in practice.

Where the water goes

A concrete slab is impervious. Water that used to soak into the ground now runs off it, and where it runs matters.

Property owners are responsible for ensuring hard surfaces do not create increased or concentrated flows onto neighbouring land. Runoff has to be directed to a lawful point of discharge — typically the kerb and channel, an inter-allotment drainage line, or a council drainage easement where council permits it. Councils also restrict building over or near stormwater infrastructure and within drainage easements, so check what is under your proposed slab before you pour.

Downstream owners have to accept natural overland flow. They do not have to accept flow that you have increased or concentrated.

Queensland's planning schemes follow the Queensland Planning Provisions structure, but each council layers its own codes and overlays on top. They are not uniform, so stormwater and earthworks provisions need to be read in your own scheme. You can check the zone, overlays and easements affecting your land on your council's planning scheme mapping and on the Queensland Globe.

Separately, a slab that meets the road at a new vehicle crossover involves work in the road reserve, which councils approve under their own process. That is not building approval, and it is easy to overlook until the concrete truck is booked.

What to do next

Ask three questions before you order concrete: what does the slab support, how much cut and fill does the pad need, and where does the water go. If the answers are "nothing", "under a metre" and "to the kerb", you are almost certainly clear. The Queensland Government's guidance on when you don't need building approval sets out the state-level position.

If you'd rather see your zone, your overlays and your likely category of assessment in one document than work through a planning scheme yourself, an instantDA planning report does that for your address for $169 — against the $800–$1,500 a town planner typically charges for a preliminary opinion. You can start a report in a few minutes.

If the slab is a pad for a shed, the shed is the approval that matters, and council approval for a shed in QLD covers the thresholds you will be measured against. If levelling the site means holding soil back, read council approval for a retaining wall before you set out, because the surcharge rule is easy to trip. And if the slab is a driveway meeting the street, council approval for a driveway covers the crossover approval.

Then confirm with your council before you pour. Concrete is unusually unforgiving of being wrong.

Frequently asked questions

Do I need council approval for a concrete slab in QLD?
A bare slab at ground level supporting nothing usually needs no building approval, because it is site work rather than building work. If the slab forms the floor or footings of a shed, garage, carport or roofed patio, it is assessed as part of that structure's building approval.
Do I need approval for a shed slab in Queensland?
The slab is not approved separately. Where the shed itself needs building approval, the private certifier assesses the slab, footings and tie-down points as part of that approval. Where the shed is small enough to be accepted development, the slab goes with it.
How much can I cut or fill without approval in QLD?
Filling or excavation for a building or structure is accepted development where the cut or fill is no deeper than 1m above or below the natural ground surface and the embankment gradients stay within the limits set by soil type in the Building Regulation 2021.
Does a concrete slab need a retaining wall approval?
Only if a wall is involved. A retaining wall is accepted development where there is no surcharge loading over its zone of influence, the total height of the wall and the fill or cut it retains is no more than 1m, and it is no closer than 1.5m to a building or another wall.
Can I direct water off my slab onto the neighbour's land?
No. Owners must not create increased or concentrated flows onto neighbouring land. Runoff has to reach a lawful point of discharge — commonly the kerb and channel, an inter-allotment drainage line, or a council drainage easement where council permits it.
Do I need approval for a concrete driveway in Queensland?
The driveway surface on your own land generally sits outside building approval, but the crossover where it meets the road involves work in the road reserve and needs council approval under its own process. Check with your council before booking the pour.